The observations came during a hearing on MMRDA's plea seeking diversion of mangrove forest land for an 8.85-km elevated driverless pod car network in BKC
The observations came during a hearing on MMRDA's plea seeking diversion of mangrove forest land for an 8.85-km elevated driverless pod car network in BKC

'Tree plantation a formality?': Bombay HC flags ecological damage from development projects

The High Court questioned the effectiveness of compensatory plantation and stressed the need to balance environmental conservation with rapid urbanisation

The Bombay High Court on Wednesday expressed concern over ecological damage caused by infrastructure development projects, emphasising that environmental restoration must proceed simultaneously with rapid urbanisation rather than remain a mere paperwork exercise.

A bench comprising Chief Justice Mahesh Chandra Tripathi and Justice Advait Sethna observed that state agencies in Maharashtra cannot indiscriminately clear green cover for infrastructure projects while treating compensatory plantation as a formality.

The observations came during the hearing of a petition filed by the Mumbai Metropolitan Region Development Authority (MMRDA) seeking permission to divert 0.2869 hectares of mangrove forest land for a transport infrastructure project.

๐—›๐—– ๐—พ๐˜‚๐—ฒ๐˜€๐˜๐—ถ๐—ผ๐—ป๐˜€ ๐—ฑ๐—ฒ๐—น๐—ฎ๐˜†๐—ฒ๐—ฑ ๐—ฎ๐—ณ๐—ณ๐—ผ๐—ฟ๐—ฒ๐˜€๐˜๐—ฎ๐˜๐—ถ๐—ผ๐—ป

The court stressed that authorities must initiate afforestation efforts in advance instead of seeking permission to remove existing green cover and undertaking ecological restoration subsequently.

"Why damage the ecosystem? The efforts of replantation have to be sincere and genuine. Once we give permission then efforts are taken for plantation. That would take years," the High Court observed.

The bench noted that mature trees and mangroves affected by infrastructure projects were often replaced with saplings that could take several years to grow, with no certainty regarding their survival.

"There has to be a balance in the ecosystem. We are disturbing the ecosystem on account of development. Development is also important. But the rehabilitation of the environment has to move simultaneously," the court said.

The bench further observed that newly planted trees could take five to ten years to mature, leaving an immediate ecological deficit.

๐Ÿด.๐Ÿด๐Ÿฑ-๐—ธ๐—บ ๐—ฑ๐—ฟ๐—ถ๐˜ƒ๐—ฒ๐—ฟ๐—น๐—ฒ๐˜€๐˜€ ๐—ฝ๐—ผ๐—ฑ ๐—ฐ๐—ฎ๐—ฟ ๐—ฝ๐—ฟ๐—ผ๐—ท๐—ฒ๐—ฐ๐˜ ๐—ถ๐—ป ๐—•๐—ž๐—–

The MMRDA has sought permission to divert mangrove forest land for the construction of an 8.85-km elevated Automated Rapid Transit System (ARTS) in Mumbai's Bandra-Kurla Complex (BKC).

The proposed driverless electric pod car network is aimed at improving last-mile connectivity and easing persistent traffic congestion in Mumbai's prominent commercial district.

Appearing for the MMRDA, advocate Saket Mone told the court that the elevated transport corridor was vital for improving connectivity in the business district.

In its petition, the state-run development authority maintained that no mangroves would be felled for the project, although six trees would be affected.

The MMRDA assured the court that it would undertake compensatory plantation of 100 trees.

๐—–๐—ผ๐˜‚๐—ฟ๐˜ ๐—พ๐˜‚๐—ฒ๐˜€๐˜๐—ถ๐—ผ๐—ป๐˜€ ๐—ฐ๐—ผ๐—บ๐—ฝ๐—ฒ๐—ป๐˜€๐—ฎ๐˜๐—ผ๐—ฟ๐˜† ๐—ฝ๐—น๐—ฎ๐—ป๐˜๐—ฎ๐˜๐—ถ๐—ผ๐—ป ๐—บ๐—ฒ๐—ฎ๐˜€๐˜‚๐—ฟ๐—ฒ๐˜€

The bench questioned why compensatory plantation had not been initiated when the infrastructure project was first conceptualised.

Maharashtra Advocate General Milind Sathe explained that the shortage of suitable saline land posed challenges to mangrove plantation.

He also submitted that saplings were generally planted during the pre-monsoon period to improve their chances of long-term survival.

The court, however, emphasised that plantation efforts must translate into tangible ecological restoration rather than merely fulfil administrative requirements.

๐—›๐—– ๐˜€๐—ฒ๐—ฒ๐—ธ๐˜€ ๐—ณ๐—ถ๐˜ƒ๐—ฒ-๐˜†๐—ฒ๐—ฎ๐—ฟ ๐—ด๐—ฟ๐—ฒ๐—ฒ๐—ป ๐—ฐ๐—ผ๐˜ƒ๐—ฒ๐—ฟ ๐—ฑ๐—ฎ๐˜๐—ฎ

Before passing orders on the MMRDA's petition, the High Court directed the Maharashtra government to furnish concrete data on the state's green cover over the past five years.

The government has been asked to provide details regarding total green cover, losses sustained during the period and the survival rates of saplings planted as part of compensatory afforestation initiatives.

The directions seek to assess the effectiveness of ecological restoration measures undertaken alongside infrastructure development.

The High Court posted the matter for further hearing on November 30.