The highway's Maharashtra section had recorded a 44 per cent cost escalation, while officials targeted April 2027 for completion 
Special Reports

The 8-km gap in a 592-km highway, and the Rs 5,500-crore cost escalation

An Indian Express investigation had traced delays across five stretches to contractors facing financial troubles, regulatory probes and other obstacles

Nearly two decades after the Mumbai-Goa highway project was conceived, around eight kilometres of the crucial corridor remain unfinished, with the estimated cost of its Maharashtra section rising by more than Rs 5,500 crore, an investigation by The Indian Express has revealed.

The investigation found that contractors associated with five delayed stretches of the 592-km highway included companies linked to a former Congress minister, a businessman facing an Enforcement Directorate (ED) investigation, a firm that had figured on the Reserve Bank of India's list of major defaulters, and a venture headed by a former senior bureaucrat.

The five unfinished stretches, spread across the 472-km Maharashtra section, have recorded cost overruns exceeding Rs 2,000 crore in the packages examined, according to the newspaper's findings.

The overall estimated cost of the Maharashtra section has increased by approximately 44 per cent, from Rs 12,532 crore to more than Rs 18,100 crore.

The delays have continued despite the highway being nearly 99 per cent complete, with individual pending packages reporting progress ranging from 89 per cent to 98.5 per cent.

Union Road Transport and Highways Minister Nitin Gadkari had publicly expressed frustration over the prolonged delays while inaugurating a 5.15-km corridor at Porvorim in Goa on September 9.

Gadkari said he was "ashamed for the delay that has happened" and indicated that he would not attend the highway's inauguration, expected next year.

The Ministry of Road Transport and Highways (MoRTH) has now set April 2027 as the revised deadline for completing the remaining work.

๐—ง๐˜„๐—ผ ๐—ฑ๐—ฒ๐—ฐ๐—ฎ๐—ฑ๐—ฒ๐˜€ ๐—ผ๐—ณ ๐—ฑ๐—ฒ๐—น๐—ฎ๐˜†๐˜€

The Mumbai-Goa highway was conceived in 2006 as part of the four-laning of National Highway 66, envisioned as an economic corridor extending from Panvel near Mumbai to Kanyakumari.

Construction began in October 2007 on a 21-km stretch near the Maharashtra-Goa border, which was completed in 2013.

Most of the remaining stretches were sanctioned during 2015-16, with contracts awarded in 2017-18.

In December 2016, the government informed Parliament that the project would be completed by December 2018. The deadline was subsequently extended to 2021, but construction continued to face setbacks.

Some unfinished works were eventually awarded to new contractors, including one package as recently as October 2025.

According to The Indian Express investigation, the pending work includes two bypasses measuring approximately three kilometres, a 192-metre bridge, a 1.8-km flyover, hill cutting across four locations covering 1.5 km, and other road construction.

The 120-km Goa section, extending from the Maharashtra border to Panaji, has already been completed.

๐—–๐—ผ๐—ป๐˜๐—ฟ๐—ฎ๐—ฐ๐˜๐—ผ๐—ฟ๐˜€ ๐˜‚๐—ป๐—ฑ๐—ฒ๐—ฟ ๐˜€๐—ฐ๐—ฟ๐˜‚๐˜๐—ถ๐—ป๐˜†

The investigation identified financial difficulties, loan defaults, land acquisition disputes, delays in statutory clearances and local protests among the factors responsible for the prolonged construction.

The Panvel-Kasu and Kasu-Indapur stretches, together covering approximately 84.6 km, were originally awarded to a consortium led by Supreme Infrastructure India.

The company subsequently faced financial difficulties and appeared on the RBI's list of the top 100 bank defaulters in 2019.

The original contract was terminated in 2021, following which the unfinished works were awarded to other companies.

The Panvel-Kasu package was awarded in March 2023 to J M Mhatre Infra Pvt Ltd, a company associated with politician-businessman J M Mhatre, who is under ED investigation over alleged fraud involving forest land.

The Indian Express reported that Mhatre, formerly associated with the Peasants and Workers Party, joined the BJP in 2025.

The Kasu-Indapur package was awarded to Indore-based Kalyan Toll Infrastructure Ltd in November 2022.

Both sections have reported approximately 97.75 per cent completion, while financial settlement relating to the original contracts remains under arbitration.

๐—ฃ๐—ผ๐—น๐—ถ๐˜๐—ถ๐—ฐ๐—ฎ๐—น ๐—ฎ๐—ป๐—ฑ ๐—ฏ๐˜‚๐—ฟ๐—ฒ๐—ฎ๐˜‚๐—ฐ๐—ฟ๐—ฎ๐˜๐—ถ๐—ฐ ๐—น๐—ถ๐—ป๐—ธ๐˜€

The Indapur-Wadpale stretch, measuring 26.75 km, was originally awarded to a joint venture involving Chetak Enterprises, owned by former Rajasthan Congress minister Udai Lal Anjana, and APCO Infratech.

The contract was terminated in June 2025 after delays attributed to forest clearances, utility shifting, land acquisition and other preparatory work.

The remaining construction was awarded to Jaipur-based LNA Infraprojects in October 2025, with completion targeted for March 2027.

According to The Indian Express, the package is approximately 89 per cent complete, while its estimated cost has risen from Rs 1,203 crore to Rs 1,657 crore.

Another delayed package, the 34.45-km Parashuram Ghat-Arawali stretch, involves a joint venture between Chetak Enterprises and Eagle Infra India Ltd.

The project, which includes the unfinished 1.8-km Chiplun flyover, has experienced substantial cost escalation, from Rs 983 crore to Rs 2,226 crore, an increase of approximately 126 per cent.

Land acquisition difficulties and court cases were cited among the reasons for the delays. The package is reportedly 98.5 per cent complete, with the flyover expected to open for commercial operations in November.

The fifth delayed stretch, from Arawali to Kante, covers 39.24 km and was initially awarded to a joint venture involving MEP Infrastructure Developers and San Jose India.

MEP subsequently defaulted on a Rs 128-crore loan and entered insolvency proceedings in March 2024.

The remaining work was awarded to Hazoor Infra Projects, a subsidiary of Hazoor Multi Projects, whose chairman and managing director, Radheshyam Mopalwar, previously headed the Maharashtra State Road Development Corporation and oversaw the Samruddhi Expressway project.

The package is approximately 95 per cent complete, with its estimated cost increasing from Rs 1,102 crore to Rs 1,443 crore.

The Indian Express reported that several contractors and individuals approached for comment did not respond, while representatives of some companies provided explanations concerning their involvement or the status of pending work.

๐—š๐—ผ๐˜ƒ๐˜ ๐˜€๐—ฒ๐˜๐˜€ ๐—ป๐—ฒ๐˜„ ๐—ฑ๐—ฒ๐—ฎ๐—ฑ๐—น๐—ถ๐—ป๐—ฒ

MoRTH Secretary V Umashankar told The Indian Express that substantial progress had been achieved on the delayed sections during the past two years.

"In the last two years, a lot of work was done on stalled stretches and 99% of the highway is through now. All pending work will be completed by April next year," he said.

Ministry officials attributed the overall cost escalation primarily to land acquisition, modifications necessitated by site constraints and the construction of additional underpasses following demands from local residents.

A senior MoRTH official described the project as an example of how major highway construction could be disrupted by shortcomings in planning, financial management and contract execution.

The official said the ministry had strengthened its procedures to ensure that environmental and forest clearances were obtained before tenders were invited.

Under the revised approach, at least 90 per cent of the required land must also be acquired before construction contracts are awarded.

The ministry has additionally begun terminating contracts where necessary and introduced cost limits for projects implemented through state public works departments.

With the Goa section already completed, finishing the remaining eight kilometres in Maharashtra would remove the outstanding gaps in the corridor linking the Mumbai region with Panaji.

However, after repeated deadline extensions, the government's April 2027 target remains the next major milestone for the long-delayed highway project.