The Maharashtra Forest Department has ordered an immediate halt to construction at Adani Green Energy Limited's 1,500-MW Tarali pumped storage hydropower project in Satara district, citing the absence of mandatory approval from the National Board for Wildlife (NBWL).
The stop-work order was issued on November 13, hours after The Indian Express published an investigation revealing that the company had sought to revise the project's estimated cost from Rs 5,675 crore to Rs 56.75 crore, a reduction of 99 per cent.
According to the newspaper's investigation, the revised estimate would reduce the amount payable towards wildlife conservation at the Sahyadri Tiger Reserve from Rs 227 crore to approximately Rs 2.27 crore.
The forest department's action concerns the Tarali Pumped Storage Project in Patan taluka, which falls within the deemed eco-sensitive zone of the Sahyadri Tiger Reserve.
๐ช๐ผ๐ฟ๐ธ ๐ต๐ฎ๐น๐๐ฒ๐ฑ ๐ผ๐๐ฒ๐ฟ ๐ฐ๐น๐ฒ๐ฎ๐ฟ๐ฎ๐ป๐ฐ๐ฒ
The forest department issued show-cause notices to the project's manager and an authorised Adani representative after an inspection found that construction activities had begun without prior NBWL approval.
The notices were issued by Satara Deputy Conservator of Forests Amol Satpute and Patan Range Forest Officer R S Nalawade.
The department described the commencement of work without the required clearance as a serious matter involving possible violations of forest and wildlife protection laws.
It directed that all construction activities at the project site be suspended until the necessary approvals were obtained from the competent authorities and the NBWL.
The department also sought a written explanation within three days, asking the company to clarify the legal basis on which construction had commenced.
Additionally, officials demanded statutory clearance documents, project maps and original or attested copies of permissions for tree cutting at the site.
The notices warned that failure to provide a satisfactory explanation and supporting documents could invite legal and punitive action under the applicable forest laws.
The Indian Express reported that construction was underway when its reporters visited the project site.
๐ฃ๐ฟ๐ผ๐ท๐ฒ๐ฐ๐ ๐ฐ๐ผ๐๐ ๐๐ป๐ฑ๐ฒ๐ฟ ๐๐ฐ๐ฟ๐๐๐ถ๐ป๐
The controversy began after the company's September 8, 2026, affidavit sought to revise the project's estimated cost to Rs 56.75 crore, compared with Rs 5,675 crore mentioned in its February 2025 environmental clearance.
Under the conditions prescribed by the State Board for Wildlife, the company was required to deposit four per cent of the project cost towards conservation and protection activities at the Sahyadri Tiger Reserve.
Based on the original estimate, the amount worked out to Rs 227 crore.
However, the revised figure reduced the corresponding conservation contribution to approximately Rs 2.27 crore.
According to The Indian Express, the Maharashtra Forest Department accepted the revised figure, following which the company deposited Rs 56.75 lakh, equivalent to one per cent of the revised project cost, into the tiger reserve's bank account.
The remaining three per cent, approximately Rs 1.71 crore, was to be deposited after NBWL approval.
On March 24, Principal Chief Conservator of Forests (Wildlife) M Srinivas Reddy had initially directed the company to deposit Rs 227 crore and submit an affidavit agreeing to comply with 14 additional conditions before its proposal could be forwarded to the NBWL.
However, on October 12, Reddy communicated acceptance of the revised estimate and instructed the company to make the initial deposit.
๐๐ฒ๐ป๐๐ฟ๐ฒ ๐ผ๐ฟ๐ฑ๐ฒ๐ฟ๐ ๐ฝ๐ฟ๐ผ๐ฏ๐ฒ
The project came under scrutiny after Rohan Bhate, honorary wildlife warden of Satara district, filed complaints on October 30 through the Prime Minister's grievance redressal portal and the Maharashtra government's Aaple Sarkar portal.
Bhate questioned the revised project estimate and sought an investigation into the matter.
On November 6, the Union Ministry of Environment, Forest and Climate Change directed the Maharashtra Forest Department to investigate the allegations on priority.
The proposed project covers approximately 150.74 hectares of non-forest land across Nivade, Tondoshi, Kalambe and Jalu villages in Satara district.
Its location near the Koyna Wildlife Sanctuary, which forms part of the Sahyadri Tiger Reserve, has brought the project's environmental obligations under scrutiny.
๐๐ฑ๐ฎ๐ป๐ถ ๐ฑ๐ฒ๐ณ๐ฒ๐ป๐ฑ๐ ๐ฝ๐ฟ๐ผ๐ท๐ฒ๐ฐ๐
Responding to the developments on Monday, Adani Green Energy maintained that the Tarali project was being developed in compliance with applicable statutory requirements and directions issued by competent authorities.
The company said no component of the project fell within a notified protected area and that no forest land was involved.
It stated that a no-objection certificate confirming the absence of forest land had been obtained on January 23, 2024.
Adani Green Energy further said the project had received environmental clearance on February 11, 2025, followed by consent to establish from the Maharashtra Pollution Control Board on April 7, 2025.
The company maintained that construction began only after obtaining the necessary permissions from the relevant authorities.
It also said the wildlife clearance process had been initiated as part of compliance with environmental clearance conditions.
According to the company, its proposal for survey and investigation activities was submitted in January 2025 and subsequently recommended by the State Board for Wildlife.
The main project proposal has since been submitted to the NBWL and remains under consideration.
The company has separately disputed allegations that it sought to reduce its overall project cost to avoid statutory conservation payments, maintaining that the lower figure related to survey and investigation expenses rather than the project's total estimated cost.
The forest department's stop-work direction will remain in force until the necessary approvals are obtained, while the investigation into the project's cost revision and conservation obligations continues.